Dalrymple Bay Coal Terminal (DBCT) undertook a project from 2014 to 2015 to upgrade the telemetry, emergency stop system and associated devices along six of their conveyors and replace them with an AS4024.1 compliant PLC and remote I/O system.
Removing End of Life (EOL) hardware to improve systems reliability and diagnostics
Friday, 22 January 2021
ATSYS successfully delivered the upgrade project to DBCT, introducing many benefits to the operation of the site, while overcoming the many challenges encountered throughout the project. Some of these benefits included:
Replacement of End-of-Life PLC Hardware, reducing communications drop-outs and spurious trips
Providing a higher level of diagnostics
PLC hardware which conforms with standards for machine safety
A new DLR Fibre Network to ensure redundancy and improve reliability of communications
Project Title
DBCT Telemetry and Emergency Stop Upgrade
Location
Mackay, QLD
Client
Dalrymple Bay Coal Terminal
Project Value
$250K
Contact for more information
Principal Consultant - Infrastructure